 □  1.)  Lot Scrape
 □  2.)
 Slab Backfill
 □  3.)  Plumbing Rough-In
 □  4.)  Soil Treatment
 □  5.)  Slab Pre-Pour and Pour
 □  6.)  Block
 □  7.)  Lintel Pour
 □  8.)  Trusses Deliver

Frame Schedule

 □ 1.)  Frame 
 □ 2.)
Glass Block Windows-Install 
 □ 3.)  Fireplace 
 □ 4.)  Roofing-Flashing, Felt, Valley Metal 
 □ 5.)  Window Installation 
 □ 6.)  Aluminum & Soffit Fascia 
 □ 7.)  Plumbing Tub Set 
 □ 8.) Gas Rough In 
 □ 9.)  HVAC Rough 
 □ 10.)  Electrical Rough 
 □ 11.)  Low Voltage Rough 
 □ 12.)  Roofing-Install Shingle-Final 
 □ 13.)  Insulation-Batt and Poly-cel 
 □ 14.)  Vinyl Siding 
 □ 15.)  Decorative Cement Coating-Lathe Work
 □ 16.)  Decorative Cement Coating-Finish

Trim Schedule

□  1.)  Drywall 
2.)
Overhead Garage Door Installation
□  3.)
Trim Carpentry

4.)
Blown Insulation

5.)
Cabinet Installation

6.)
Cabinets: Solid Surface Tops-Install

7.)
Cabinets: Cultured Marble Tops-Install

8.)
Interior Paint

9.)
Rough Grade Walks & Drives

10.)
Exterior Paint

11.)
Walks / Drive-Pour

Final Schedule

□  1.)  Final Grade 

2.)
Fencing

3.)
Landscape

4.)
Sprinkler Systems

5.)
Mailbox

6.)
Sod

7.)
Wall Tile Installation

8.)
Floor Tile Installation

9.)
Plumbing Trim Final

10.)
Gas Trim

11.)
HVAC Trim

12.)
Electrical Final

13.)
Low Voltage Final

14.)
Rough Clean

15.)
Vinyl Flooring

16.)
Trim Carpentry Lock Out

17.)
Shower Enclosures

18.)
Mirrors

19.)
Ventilated Shelving

20.)
Blinds-Install

21.)
Screen Enclosures

22.)
Carpet Installation

23.)
Final Clean-Re-Clean

24.)
Paint Punch out

25.)
Final Punch Out Checklist with Production Manager

 